Hurricane Rebuild Update

Hurricane Rebuild Update: (June 19, 2025)-

  • The Electricians have finished down stairs and the inspection completed.
  • On June 27th we will be holding a Member Work Day at Lodge (8am – 4pm)
    • We will install insulation on the 1st floor. We will remove as much of the old ductwork downstairs as we can.
    • Prep for drywall installation.
    • Also remove the old flue (exterior vent pipe) from our old gas system.
  • On July 5th we will have our drywall party and install the drywall. Drywall screw inspection will be completed soon after.
  • Air conditioning will begin being installed on the 2nd floor
  • We are expecting to have drywall finished and air conditioning installed and completed on the 2nd floor no later than the beginning of August.